PROPOSED INFILLING OF WETLANDS ON ERF 29654, BLUE DOWNS (DEA&DP REFERENCE: 16/3/3/1/A3/54/2056/20)

This Basic Assessment Report has been revised and is being made available for a 30-day commenting period to the registered I&APs and relevant Organs of State for their perusal and comment. The commenting period commences on 25 May 2021 and closes on 25 June 2021.

At the end of the commenting period, all comments will be captured and addressed and included in a Final Basic Assessment Report which will be submitted to the competent authority, DEA&DP, for the environmental decision.

The BAR is available for perusal at www.enviropart.co.za. Furthermore, a physical copy of the BAR is available for on-site reading at the Mfuleni Public Library for the duration of the commenting period.

Comments on this report may be submitted on or before 25 June 2021 to The Environmental Partnership at:

P O Box 945, Cape Town, 8000
Tel: 021 422 0999; Fax: 021 422 0998
WhatsApp (messages only): 068 493 5890
Email: comments@enviropart.co.za

INTRODUCTION

The City of Cape Town, the proponent, is the holder of an environmental authorisation for an integrated development on Erf 29654 (formerly Portion 2 of the remainder of Farm No. 451 and incorporating a Portion of Erf 1892) in Bardale, Blue Downs. The site is bound to the north by Fountain Village, to the west by Faure Klipfontein Road, and to the east by the Blue Downs Municipal Swimming Pool grounds (Please see Appendix A1: Locality Map).

The proponent has an approved Environmental Authorisation (EA) which was issued on
16 November 2010 (Ref. No. E12/2/3/1-A4/53-0988/10), amended on 30 October 2013 (Ref. No. 16/3/1/5/A4/5/1026/13), 03 November 2015 (Ref. No. 16/3/3/5/A4/5/3017/15) as well as on
22 July 2020 (Ref. No. 16/3/3/5/A4/5/3019/20). See Appendix E3: Existing approval(s) – Environmental Authorisations)

The EA authorises the construction of Single Residential 1 erven and Single Residential 2 erven, community facilities, public open spaces and two retention ponds. The affordable housing development on Erven 29654, herein referred to as ‘the site’, will be developed to make provision for adequate facilities and amenities to promote a conducive living environment and to enhance the lifestyle of the residents.

There are two wetlands located on the site, one in the northern portion of the site and the other towards the southern portion of the site. Both wetlands are fed by groundwater and are heavily degraded due to activities such as dumping, excavation, grazing and loss of almost all indigenous vegetation (Please see Appendix A2: Sensitivity map).

At the time of the previous basic assessment process, the two wetlands were not identified and, as such, not included in the Basic Assessment Report. The associated listed activity was not included in the application form to the Department of Environmental Affairs & Development Planning at the time and therefore has not been authorised.

This Basic Assessment Report is for the infilling or depositing of any material greater than 10 cubic metres into the two aforementioned wetlands (W1 and W2) which triggers Activity 19 of Listing Notice (GNR No. 983 of 2014) of the National Environmental Management: Environmental Impact Assessment (EIA) Regulations, as amended.

PROJECT PROPOSAL

The project proposal for this Basic Assessment Report entails infilling of wetlands W1 and W2. The infilling of the wetlands is for the development of stormwater ponds on the site as well hardening of the surrounding area. Infilling of the wetlands is in accordance with the approved layout for the housing development.

The site development plan has been updated slightly, including the following minor changes:

  • Access location switched for 2 of the cul de sacs for drainage purposes. This resulted in resizing / realignment of the existing erven;
  • Access granted to the services servitude from the internal road. Size of the CO1 property was increased; and
  • 5m pinch point close to London Way was expanded by removing an erf and accommodating it in the crescent.

The above changes did not result in any loss of erven nor in any other substantial changes in the site development plan. Please see the revised site development plan as Appendix B1(ii).

ALTERNATIVES

The EIA Regulations of 2014, as amended, require reasonable alternatives to the activity to be identified and assessed. Since the residential development has already been subjected to an EIA process and has been approved, there will be no alternatives to the layout. The layout has been approved and the site has been appropriately rezoned. The freshwater specialist recommends new stormwater management interventions to prevent impacts to the downstream (Kuils River) water resources due to the loss of two low-significance seasonal wetlands on-site and these have been included in the Environmental Management Programme to be implemented (See Appendix H: EMPr). Since the infilling of the wetlands will not undermine the approved development and would be suitable for development, alternatives will not be presented.

The two alternatives to be discussed in this Basic Assessment Report are thus Alternative 1 which entails the infilling of the two seasonal wetlands on the site to facilitate the implementation of the approved development and Alternative 2 which is the no-go alternative.

LEGISLATION

The 2014 NEMA Environmental Impact Assessment Regulations of 2014, as amended, apply to the proposed development and necessitate a Basic Assessment Process. The proposed development includes activities listed in GN983 of the 2014 EIA Regulations, as amended. This is:

Listing Notice 1 (GN983 of 2014, as amended)

Activity 19

The infilling or depositing of any material of more than 10 cubic metres into, or the dredging, excavation, removal or moving of soil, sand, shells, shell grit, pebbles or rock of more than 10 cubic metres from a watercourse.

IDENTIFIED POTENTIAL IMPACTS

The following impacts have been identified and assessed for Layout Alternatives 1 and 2, as well as the No-Go Alternative:

Planning and Design Phase

Loss of biodiversity associated with the loss of seasonal wetland habitat

Loss of approximately 0.6 ha of wetland habitat

Loss of the stormwater-related functions currently derived from the two seasonal wetlands on the site

Geotechnical impact of infilling the wetlands on the structures

Construction Phase

Increased runoff of sediments, cementitious waste and fuels/oils/other construction associated waste into the Kuils River system

Operational Phase

Water quality impacts in the Kuils River System

WAY FORWARD

This Basic Assessment Report has been revised and is being made available for a 30-day commenting period to the registered I&APs and relevant Organs of State for their perusal and comment. The commenting period commences on 25 May 2021 and closes on 25 June 2021.

At the end of the commenting period, all comments will be captured and addressed and included in a Final Basic Assessment Report which will be submitted to the competent authority, DEA&DP, for the environmental decision.

The BAR is available for perusal at www.enviropart.co.za. Furthermore, a physical copy of the BAR is available for on-site reading at the Nfuleni Library for the duration of the commenting period. Several copies of the Information Sheet have also been placed at the Mfuleni Public Library.

Comments on this report may be submitted on or before 25 June 2021 to The Environmental Partnership at:

P O Box 945, Cape Town, 8000
Tel: 021 422 0999; Fax: 021 422 0998
WhatsApp (messages only): 068 493 5890
Email: comments@enviropart.co.za

For a concise yet comprehensive summary of the Basic Assessment Report, please see this Information sheet May 2021

For the full Basic Assessment Report, please see Aloe Ridge Revised DBAR- Infilling of Wetlands – May 2021

Contact Details (for public comment)

Tel: 021-422 0999

Fax: 021-422 0998

Email: comments@enviropart.co.za

Physical Address: 56 Shortmarket Street,
(3rd Floor),
Cape Town,
8001

Postal Address: P.O. Box 945, Cape Town, 8000

ALL PUBLIC ITEMS

PROPOSED INFILLING OF WETLANDS ON ERF 29654, BLUE DOWNS (DEA&DP REFERENCE: 16/3/3/1/A3/54/2056/20)

PROPOSED INFILLING OF WETLANDS ON ERF 29654, BLUE DOWNS (DEA&DP REFERENCE: 16/3/3/1/A3/54/2056/20)

PROPOSED HOUSING DEVELOPMENT ON FARM 920/RE, SIR LOWRY’S PASS VILLAGE, SOMERSET WEST (DEA&DP REFERENCE: 16/3/3/1/A3/54/2056/20)

PROPOSED HOUSING DEVELOPMENT ON FARM 920/RE, SIR LOWRY’S PASS VILLAGE, SOMERSET WEST (DEA&DP REFERENCE: 16/3/3/1/A3/54/2056/20)

NOTIFICATION OF ENVIRONMENTAL AUTHORISATION – ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED WASTE TRANSFER FACILITY ON A PORTION OF THE REMAINDER OF FARM NO. 279, STELLENBOSCH. DEA&DP REF. NO. 16/3/3/1/B4/45/1063/20

NOTIFICATION OF ENVIRONMENTAL AUTHORISATION – ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED WASTE TRANSFER FACILITY ON A PORTION OF THE REMAINDER OF FARM NO. 279, STELLENBOSCH. DEA&DP REF. NO. 16/3/3/1/B4/45/1063/20

THE PROPOSED EXTENSION OF THE BLACK RIVER CANAL CULVERT FOR ROAD WIDENING ALONG IMAM HARON ROAD, CAPE TOWN

THE PROPOSED EXTENSION OF THE BLACK RIVER CANAL CULVERT FOR ROAD WIDENING ALONG IMAM HARON ROAD, CAPE TOWN

NOTIFICATION OF THE AMENDED ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 30297 (FORMERLY PORTION 31 OF FARM NO. 451) IN BARDALE, BLUE DOWNS DEA&DP REF. NO. 16/3/3/5/A4/5/3045/20

NOTIFICATION OF THE AMENDED ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 30297 (FORMERLY PORTION 31 OF FARM NO. 451) IN BARDALE, BLUE DOWNS DEA&DP REF. NO. 16/3/3/5/A4/5/3045/20

NOTIFICATION OF ENVIRONMENTAL AUTHORISATION – ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED CONSTRUCTION OF A CIRCULATORY TRAIL AROUND THE PRINCESS VLEI AND THE UPGRADING OF ASSOCIATED FACILITIES IN THE PRINCESS VLEI PARK, RETREAT, WESTERN CAPE. DEA&DP REFERENCE: 16/3/3/1/A6/64/2057/19

NOTIFICATION OF ENVIRONMENTAL AUTHORISATION – ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED CONSTRUCTION OF A CIRCULATORY TRAIL AROUND THE PRINCESS VLEI AND THE UPGRADING OF ASSOCIATED FACILITIES IN THE PRINCESS VLEI PARK, RETREAT, WESTERN CAPE. DEA&DP REFERENCE: 16/3/3/1/A6/64/2057/19

NOTIFICATION OF ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED CONSTRUCTION OF A RESIDENTIAL DEVELOPMENT AND ASSOCIATED INFRASTRUCTURE ON PORTION 35 OF FARM 918, SOMERSET WEST (DEA&DP REF. NO. 16/3/3/1/A3/54/2004/20)

NOTIFICATION OF ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED CONSTRUCTION OF A RESIDENTIAL DEVELOPMENT AND ASSOCIATED INFRASTRUCTURE ON PORTION 35 OF FARM 918, SOMERSET WEST (DEA&DP REF. NO. 16/3/3/1/A3/54/2004/20)

THE PROPOSED INTEGRATED RAPID TRANSPORT (IRT) SYSTEM ALONG OTTERY ROAD FROM STRANDFONTEIN ROAD TO KROMBOOM PARKWAY (M5)

THE PROPOSED INTEGRATED RAPID TRANSPORT (IRT) SYSTEM ALONG OTTERY ROAD FROM STRANDFONTEIN ROAD TO KROMBOOM PARKWAY (M5)

PROPOSED INFILLING OF WETLANDS ON ERF 29654, BLUE DOWNS

PROPOSED INFILLING OF WETLANDS ON ERF 29654, BLUE DOWNS

PROPOSED WASTE TRANSFER FACILITY ON A PORTION OF FARM 279/RE,  STELLENBOSCH

PROPOSED WASTE TRANSFER FACILITY ON A PORTION OF FARM 279/RE, STELLENBOSCH

POSTPONED: PUBLIC PARTICIPATION PROCESS FOR THE ALOE RIDGE HOUSING DEVELOPMENT ON ERF 29654

PROPOSED DEVELOPMENT OF THE ASANDA VILLAGE WETLAND PARK ON ERF 32680 AND ERF 29864, STRAND

PROPOSED DEVELOPMENT OF THE ASANDA VILLAGE WETLAND PARK ON ERF 32680 AND ERF 29864, STRAND

NOTIFICATION OF THE AMENDED ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED INFILLING OF WETLANDS ON ERVEN 454 AND 469, THE REMAINDER OF FARM NO. 616 AND THE REMAINDER OF FARM NO. 619 FOR THE ESTABLISHMENT OF THE INTEGRATED RAPID TRANSPORT SYSTEM ALONG GOVAN MBEKI ROAD, PHILIPPI, CAPE TOWN

NOTIFICATION OF THE AMENDED ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED INFILLING OF WETLANDS ON ERVEN 454 AND 469, THE REMAINDER OF FARM NO. 616 AND THE REMAINDER OF FARM NO. 619 FOR THE ESTABLISHMENT OF THE INTEGRATED RAPID TRANSPORT SYSTEM ALONG GOVAN MBEKI ROAD, PHILIPPI, CAPE TOWN

NOTIFICATION OF THE AVAILABILITY OF THE BASIC ASSESSMENT REPORT FOR COMMENT AND PERUSAL FOR PROPOSED HOUSING DEVELOPMENT ON FARM 920, SIR LOWRY’S PASS VILLAGE, SOMERSET WEST

NOTIFICATION OF THE AVAILABILITY OF THE BASIC ASSESSMENT REPORT FOR COMMENT AND PERUSAL FOR PROPOSED HOUSING DEVELOPMENT ON FARM 920, SIR LOWRY’S PASS VILLAGE, SOMERSET WEST

NOTIFICATION OF THE AMENDED ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 29654 IN BARDALE, BLUE DOWNS DEA&DP REF. NO. 16/3/3/5/A4/5/3019/20

NOTIFICATION OF THE AMENDED ENVIRONMENTAL AUTHORISATION FOR THE PROPOSED RESIDENTIAL DEVELOPMENT ON ERF 29654 IN BARDALE, BLUE DOWNS DEA&DP REF. NO. 16/3/3/5/A4/5/3019/20

NOTIFICATION OF THE AVAILABILITY OF THE MAINTENANCE MANAGEMENT PLAN FOR CHAPMANS PEAK DRIVE

NOTIFICATION OF THE AVAILABILITY OF THE MAINTENANCE MANAGEMENT PLAN FOR CHAPMANS PEAK DRIVE

NOTIFICATION OF THE AVAILABILITY OF THE BASIC ASSESSMENT REPORT FOR COMMENT AND PERUSAL FOR THE PROPOSED CONSTRUCTION OF A CIRCULATORY TRAIL AND UPGRADING OF THE ECO-CENTRE ADJACENT TO PRINCESS VLEI, RETREAT / GRASSY PARK

NOTIFICATION OF THE AVAILABILITY OF THE BASIC ASSESSMENT REPORT FOR COMMENT AND PERUSAL FOR THE PROPOSED CONSTRUCTION OF A CIRCULATORY TRAIL AND UPGRADING OF THE ECO-CENTRE ADJACENT TO PRINCESS VLEI, RETREAT / GRASSY PARK